Bidding for European public contracts without a subsidiary: consortium, another entity’s capacities or a commercial agent
A German manufacturer targeting a French hospital, or a French SME bidding for a Belgian university, does not need a local subsidiary. EU law offers several set-ups. The right one depends on two questions: who carries the risk, and who gets paid.
The common framework: Directive 2014/24/EU
Above the EU thresholds, public contracts follow Directive 2014/24/EU, transposed in every member state. It guarantees that a company from any EU country can bid for a contract awarded in another EU country. Below the thresholds, each country sets its own procedures.
First set-up: a group of economic operators
The directive allows groups of economic operators to bid together (Article 19). A group may rely on the capacities of each of its members to meet the selection criteria (Article 63).
In France, the joint consortium (groupement conjoint) goes further: each member commits to its own share and invoices it directly to the buyer. The manufacturer is paid without an intermediary. Elsewhere, rules vary. When a group relies on one member’s financial standing, the buyer may require joint and several liability.
Second set-up: relying on another entity’s capacities
A bidder may also rely on the capacities of other entities, whatever the legal links between them. It must prove that it will have those resources, for example by producing a written commitment from the entity concerned.
One limit matters for professional experience: the other entity must itself perform the work for which its capacities are relied on.
Third set-up: a commercial agent
The manufacturer bids in its own name. The agent spots the tender, prepares the file, follows submission and performance, and earns a commission. This set-up is governed not by procurement law but by a commercial agency contract between manufacturer and agent.
It has two advantages: the manufacturer remains solely responsible for its equipment, and the agent advances no cash.
The ESPD simplifies bidding across Europe
The European Single Procurement Document (ESPD) is a self-declaration form common to every EU country. At the bidding stage it replaces certificates; only the winner then provides the originals. The European Commission’s eCertis database shows, country by country, which document matches each criterion.
Which set-up to choose?
| Set-up | Who signs the contract | Who is paid | Manufacturer’s risk |
|---|---|---|---|
| Joint consortium (France) | Each member, for its share | Each member, directly | Limited to its share |
| Jointly liable group | All members | As set in the consortium agreement | Shared across the whole contract |
| Another entity’s capacities | The bidder alone | The bidder | Carried by the bidder |
| Commercial agent | The manufacturer alone | The manufacturer, who pays the commission | Carried by the manufacturer |
ESTRAMAR uses the joint consortium in France, where direct payment is provided for. In other countries it works as a commercial agent by default, unless local rules offer an equivalent mechanism.